Project Schedule/Status
Last Updated August 2020
Currently, the project is in the "Construction" phase.
The demolition of the old WSSC facilities was completed in 2009. Construction of the beginner level bicycle pump track, learning pavilion, picnic area, and playgrounds was completed in 2019. The current construction phase includes an intermediate level bicycle pump track and a bicycle skills course.
A summary of the project milestones follows:
- Fall 2017 – Summer 2020 – Design and construction of the park
- Summer 2020 – Fall 2020 – Post construction / As-built drawings
- Fall/Winter 2020 – Grand Opening
Actual dates for the completion of the milestones are subject to change dependent upon weather conditions and COVID-19 updates.
Project Contact
Joseph “JJ” Arce, Central Area Park Planner
Joseph.arce@pgparks.com
301-699-2437